10. MAINTENANCE
Disconnect the power supply before any maintenance operation, both of the refrigerated
cabinet and of the condensing unit.
Maintenance work must be carried out by a qualified technician.
10.1. ROUTINE MAINTENANCE
Ensure smooth operation over time of the equipment by performing periodic/preventive checks and maintenance.
10.1.1. INSPECTING AFTER DELIVERY
The following table lists a series of controls and activities that need to be carried out according to the recommended frequency.
OPERATION
FREQUENCY
WEEKLY MONTHLY AT 6-MONTHLY
INTERVALS
YEARLY
Check that the condensation water drain system works
correctly.
■
Check that there are no refrigerant gas leaks and that the
refrigerant system is working properly.
■
Check that the maintenance status of the electrical system is
in complete safety.
■
Check that the door seals and the door itself close properly.
■
Check the correct electronic control setting.
■
Check the condition of the sponge of the refrigeration unit
for mould.
■
Check that the refrigerating unit tray is not full.
■