3.Installation of road gate machine
3.1 Construction preparation:
1. Determine the gate pre-installation position according to the selected
integrated gate direction and the field installation situation.
The gate is divided into left fixed gate and right gate, defined as follows:
facing the front of the main engine (no side of the main shaft), the right rod falls
to the left fixed gate, and the lever falls to the left direction is the right fixed
gate.As shown in the figure below:
Left and right fixed definition of road lock
2. Lay power line and control line according to the control room or post box
(separate power line and control signal line)
3. For the non-concrete foundation or the ground is not horizontal, do the gate
foundation according to the situation.
3.2 Circuit gate installation:
1. Place the box in the installation position, open the box to determine the
position of the expansion bolt and mark.