10
.
Equipment Room (continued) 11. Owner Awareness
Does the equipment room have proper Has the owner been fully instructed on the
mechanical ventilation? proper use of refrigerant HCFC-123?
If it is required by local code, is a Does the owner have a copy of the MSDS for
self-contained breathing apparatus available? refrigerant HCFC-123?
Was the owner given a copy of the
Refrigerant Handling Guidelines?
Note: Additional time required to properly complete the start-up and commissioning, due to any
incompleteness of the of the installation, will be invoiced at prevailing rates.
This is to certify that the CenTraVac chiller(s) has/have been properly and completely installed,
and that the applicable items listed above have been satisfactorily completed.
Checklist Completed By
Signed: Date:
In accordance with your quotation and our purchase order number __________, we will therefore
require the presence of Trane service on the site, for the purpose of start-up and commissioning,
by: Date:
Note: Advance notification is required to allow scheduling of the start-up as close as possible to
the requested date.
Additional Comments/Instructions
A copy of this completed form must be submitted to the Trane Service Agency that will be
responsible for the start-up of the chiller.