CHECKOUT PROCEDURES
After installation has been completed, it is recommended that the Air Handler be checked against the following
checklist.
1.Make sure power is "OFF" at power disconnect
switch ........................................................................ [ ]
2.Check all field wiring for tight connections. See that
grounding of unit is in accord with code ................. [ ]
3.Make sure unit suspension (if used) is secure and
that there are no tools or loose debris in, around or on
top of the unit ........................................................... [ ]
4.Check all duct outlets; they must be open and unre-
stricted ...................................................................... [ ]
5.Cheek drain lines and be sure all joints are
tight .......................................................................... [ ]
6.Make sure secondary drain pan is installed ......... [ ]
7..... Cheek power supply for correct requirements per
unit nameplate ......................................................... [ ]
8.Check filters for proper size. Inform owner of proper
procedure for removal and reinstallation ............... [ ]
9.Energize the system and carefully observe its opera-
tion; make any necessary adjustment .................... [ ]
10.... Instruct owner, engineer (if applicable) on proper
operating procedure and leave Use and Care Manual
with owner ................................................................ [ ]
SUPPLEMENTARY HEATERS CHECKOUT PROCEDURES
IF A HEATER IS USED, SEE "LIMITATIONS AND RECOMMENDATIONS"
TO DETERMINE IF THE HEATER REQUIRES A SPECIAL CIRCUIT.
1. Be sure the disconnect switch is "OFF", and safety label (if any) is attached ............................... [ ]
2. Check on field wiring for tight connections and grounding according to codes ............................ [ ]
3. Check circuit protection for proper size per nameplate specifications .......................................... [ ]
4. Check control box panel -- in place and secured ........................................................................... [ ]
NOTE: OPERATION OF HEATERS MUST BE CHECKED DURING THE OPERATION CHECK OF THE
TOTAL SYSTEM.
Trane
6200 Troup Highway
Tyler, TX 75707
For more information contact
your local dealer (distributor)
03/08
The manufacturer has a policy of continuous product and product data improvement, and it reserves the
right to change design and specifications without notice.

Other manuals for Trane 2TEE3C31A1000A

Related product manuals