EasyManua.ls Logo

Trane 4TTX8048A - User Manual

Trane 4TTX8048A
26 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Loading...
18-AC95D1-5C-EN
ALL phases of this installation must comply with NATIONAL, STATE AND LOCAL CODES
IMPORTANT — This Document is customer property and is to remain with this unit. Please return to service
information pack upon completion of work.
Condensing Units
These instructions do not cover all variations in systems or provide for every possible contingency to be met in connection with
the installation. Should further information be desired or should particular problems arise which are not covered sufficiently for the
purchaser’s purposes, the matter should be referred to your installing dealer or local distributor.
Note: The manufacturer recommends installing only approved matched indoor and outdoor systems. All of the manufacture’s split
systems are AHRI rated only with TXV/EEV indoor systems. Some of the benefits of installing approved matched indoor and out-
door split systems are maximum efficiency, optimum performance and the best overall system reliability.
4TTX8
Installer’s Guide
Table of Contents
Section 1. Safety ..................................................................................... 2
Section 2. Unit Location Considerations ............................................. 3
Section 3. Unit Preparation .................................................................... 5
Section 4. Setting the Unit ..................................................................... 5
Section 5. Refrigerant Line Considerations ......................................... 6
Section 6. Refrigerant Line Routing ..................................................... 8
Section 7. Refrigerant Line Brazing ...................................................... 9
Section 8. Refrigerant Line Leak Check ............................................. 11
Section 9. Evacuation .......................................................................... 12
Section 10. Service Valves .................................................................. 12
Section 11. Electrical - Low Voltage ................................................... 13
Section 12. Electrical - High Voltage .................................................. 15
Section 13. Start Up .............................................................................. 16
Section 14. System Charge Adjustment ............................................. 17
Section 15. Checkout Procedures and Troubleshooting .................. 23
Question and Answer IconNeed help?

Do you have a question about the Trane 4TTX8048A and is the answer not in the manual?

Summary

Section 1. Safety

Section 2. Unit Location Considerations

Unit Dimensions and Weight

Details unit sizes and estimated weights for various models.

Refrigerant Piping Limits

Specifies maximum total length and vertical change for refrigerant lines.

Suggested Locations for Best Reliability

Provides guidance on optimal placement for unit performance and longevity.

Cold Climate Considerations

Offers precautions for installations in areas prone to snow and freezing temperatures.

Section 3. Unit Preparation

Prepare The Unit For Installation

Outlines steps for checking and removing the unit from its packaging.

Section 4. Setting the Unit

Pad Installation

Details requirements for installing the outdoor unit on a support pad.

Section 5. Refrigerant Line Considerations

Refrigerant Line and Service Valve Connection Sizes

Presents tables for line sizes and service valve connections based on model.

Factory Charge

Explains the factory refrigerant charge amount and verification methods.

Required Refrigerant Line Length

Guides on measuring and recording line length and vertical change.

Refrigerant Line Insulation

Emphasizes the importance of insulating the vapor line.

Section 6. Refrigerant Line Routing

Precautions

Advises on routing line sets to prevent noise and comply with codes.

Section 7. Refrigerant Line Brazing

Braze The Refrigerant Lines

Details the step-by-step process for brazing refrigerant lines.

Section 8. Refrigerant Line Leak Check

Check For Leaks

Describes the procedure for pressurizing and checking refrigerant lines for leaks.

Section 9. Evacuation

Evacuate the Refrigerant Lines and Indoor Coil

Explains how to evacuate the system to the correct vacuum level.

Section 10. Service Valves

Open the Gas Service Valve

Instructs on the proper procedure for opening the gas service valve.

Open the Liquid Service Valve

Details the safe method for opening the liquid line service valve.

Section 11. Electrical - Low Voltage

Low Voltage Maximum Wire Length

Provides a table for maximum allowable low voltage wire lengths.

Low Voltage Hook-up Diagrams

Illustrates wiring connections for various thermostat and air handler configurations.

Section 12. Electrical - High Voltage

High Voltage Power Supply

Covers requirements for high voltage power supply and wiring compliance.

High Voltage Disconnect Switch

Recommends installing a separate disconnect switch for high voltage connections.

Section 13. System Start Up

System Start Up

Outlines the sequential steps for safely starting the installed system.

Section 14. System Charge Adjustment

Temperature Measurements

Explains how to measure outdoor and indoor temperatures for charging.

Subcooling Charging in Cooling (Above 55° F Outdoor Temp.)

Details subcooling method for charging in warmer conditions.

Subcooling Charging Below 55° F Outdoor Temp.

Describes the weigh-in method for charging in cooler conditions.

Section 15. Checkout Procedures and Troubleshooting

Operational And Checkout Procedures

Lists essential checks to ensure proper system operation and safety.

Troubleshooting

Provides a guide to diagnose and resolve common system faults.

Overview

This document serves as an installer's guide for Trane Condensing Units, specifically the 4TTX8 series. It provides comprehensive instructions for the proper installation, setup, and maintenance of these outdoor units, ensuring optimal performance and reliability. The guide emphasizes adherence to national, state, and local codes throughout all installation phases.

Function Description

The Trane 4TTX8 Condensing Units are integral components of a central air conditioning system, designed to work in conjunction with an indoor evaporative coil and refrigerant lines to provide cooling for residential and commercial applications. These units are factory-charged with R-410A refrigerant, a high-pressure refrigerant that requires specific handling procedures and approved service equipment. The primary function of the condensing unit is to compress and condense the refrigerant, releasing heat to the outdoor environment, thereby facilitating the cooling cycle within the building.

Usage Features

The installation process for these condensing units is broken down into several key sections, each addressing a critical aspect of setup and operation.

  • Unit Location Considerations: This section guides installers in selecting an appropriate location for the outdoor unit. It outlines important factors such as ensuring the roof can support the unit's weight if mounted on a roof, recommending proper isolation to mitigate sound and vibration transmission, and specifying minimum clearance requirements for top discharge, access panels, and surrounding shrubbery to ensure adequate airflow and serviceability. The guide also advises against installing the unit near windows or sleeping quarters to prevent noise disturbance and suggests avoiding locations where condensation and freezing defrost vapor might annoy occupants. For cold climates, specific precautions are detailed, including elevating the unit 3-12 inches above the pad or rooftop to allow for snow and ice drainage during defrost cycles, and installing snow drift barriers if necessary.

  • Unit Preparation: Before installation, the guide instructs installers to inspect the unit for any shipping damage and report it promptly. It also provides instructions on how to safely remove the unit from its pallet by cutting the securing tabs.

  • Setting the Unit: This section focuses on pad installation, recommending that the support pad (e.g., a concrete slab) be at least 1 inch larger than the unit on all sides, separate from any building structure, level, and high enough above grade to allow for proper drainage. The pad's location must also comply with all relevant codes.

  • Refrigerant Line Considerations: This is a crucial section that details the requirements for refrigerant piping. It specifies maximum total line lengths (150 feet, including lift) and vertical change limits (50 feet). A table provides standard and alternate line sizes, as well as service valve connection sizes for different models. The guide strongly recommends insulating the vapor line and preventing direct metal-to-metal contact between the liquid and vapor lines. For retrofit applications, installers are cautioned to ensure existing refrigerant lines are the correct size, free of leaks, acid, and oil, and that all joints are brazed, not soldered.

  • Refrigerant Line Routing: This section emphasizes precautions to prevent noise and vibration transmission from the refrigerant lines into the building structure. It advises using isolation hangers when fastening lines to joists, rafters, or other framing, insulating and isolating lines that run through walls or sills, and isolating lines from all ductwork. Minimizing 90-degree turns is also recommended for efficient routing.

  • Refrigerant Line Brazing: Detailed steps are provided for brazing the refrigerant lines. This includes deburring and cleaning pipe ends, removing pressure tap caps and valve cores from service valves, purging lines with dry nitrogen, and wrapping wet rags around valve bodies to prevent heat damage during brazing. For units with field-installed external driers, installers must confirm the correct directional flow of the drier. The guide also includes a critical note on avoiding heat damage to the basepan during brazing.

  • Refrigerant Line Leak Check: After brazing, a leak check is mandatory. Installers are instructed to pressurize the refrigerant lines and evaporator coil to 150 PSIG with dry nitrogen and then check for leaks using a soapy solution at all brazed locations. Any leaks must be repaired before proceeding.

  • Evacuation: This section outlines the evacuation process to remove non-condensable gases and moisture from the system. It requires evacuating until a micron gauge reads no higher than 350 microns and then verifying that the micron gauge does not rise above 500 microns in one minute after closing off the vacuum pump.

  • Service Valves: Instructions are provided for opening both the gas and liquid service valves. This includes removing valve stem caps, turning valve stems counterclockwise to the fully open position (1/4 turn for gas, approximately five turns for liquid), and replacing caps, tightening them finger-tight plus an additional 1/6 turn to prevent leaks. Extreme caution is advised when opening the liquid line service valve due to the abrupt release of system charge if not done correctly.

  • Electrical - Low Voltage and High Voltage: This section covers electrical connections. For low voltage, a table specifies maximum wire lengths for different AWG sizes. Hook-up diagrams are provided for various thermostat and indoor unit configurations (e.g., with TEM 6, TAM 7, and Variable Speed S-Series Furnace). For high voltage, a warning about live electrical components emphasizes safety precautions. Installers must ensure the power supply matches the equipment nameplate, comply with all codes, and follow the unit's wiring diagram. A separate disconnect switch is required at the outdoor unit, and flexible electrical conduit is recommended for high voltage connections to minimize vibration transmission. Grounding the outdoor unit per code requirements is also specified.

  • Start Up: The start-up procedure includes setting the system thermostat to OFF, turning on disconnects to apply power, and waiting one hour before starting the unit if a compressor crankcase heater accessory is used and the outdoor ambient temperature is below 70°F. Finally, the thermostat is set to ON.

  • System Charge Adjustment: This critical section details how to verify and adjust the refrigerant charge.

    • Subcooling Charging (Above 55°F Outdoor Temp.): This is the recommended method for charging in cooling mode when outdoor ambient temperatures are above 55°F. Installers use refrigerant line total length and lift measurements, then consult charts (for 2, 3, 4, and 5 Ton AC units) to determine the final subcooling value. The process involves measuring liquid line temperature and pressure at the outdoor unit's service valve and using a charging chart to determine the proper liquid gauge pressure. Refrigerant is added or recovered until the liquid line temperature and gauge pressure match the chart's final subcooling value. The system must be stabilized for a minimum of 20 minutes between adjustments.
    • Subcooling Charging (Below 55°F Outdoor Temp.): For outdoor temperatures below 55°F, the subcooling charging method is not recommended. Instead, the "Weigh-In Method" is used to determine additional charge based on the length of interconnecting tubing beyond the initial 10 feet. This involves measuring the total line length, subtracting 10 feet, and multiplying by a charge multiplier (0.6 oz/ft) to calculate the amount of refrigerant to weigh in. The guide emphasizes returning in warmer weather to accurately verify the charge via subcooling.
  • Checkout Procedures and Troubleshooting: The final phase involves operational and checkout procedures to ensure proper performance. A checklist guides installers through verifying leak checks, insulation, refrigerant line security, sealed masonry passages, tight electrical connections, outdoor fan operation, free-draining indoor coil drain line, open registers and grilles, installed return air filter, correct airflow setting, and overall system operation in all modes. A comprehensive troubleshooting table is provided, listing common system faults (refrigerant circuit, electrical, and defrost) and their primary and secondary causes.

Maintenance Features

While the guide primarily focuses on installation, several aspects contribute to the long-term maintainability and reliability of the unit:

  • Proper Installation for Longevity: Adhering to the detailed installation instructions, particularly regarding refrigerant line routing, brazing, and leak checking, is fundamental to preventing future issues and ensuring the system operates efficiently for its lifespan. Correctly sized and insulated refrigerant lines, along with proper vibration isolation, reduce wear and tear.
  • System Charge Adjustment: The emphasis on accurate system charge adjustment, using either subcooling or weigh-in methods, is a critical maintenance-related feature. An improperly charged system can lead to reduced efficiency, increased energy consumption, and premature component failure. The guide's instructions ensure the system is charged correctly from the outset, minimizing the need for future corrective maintenance related to charge issues.
  • Service Valve Design: The service valves are designed for ease of access during charging and recovery, allowing technicians to connect gauges and perform necessary adjustments. The instructions for opening and closing these valves, including replacing caps and tightening them correctly, are crucial for preventing refrigerant leaks over time.
  • Troubleshooting Guide: The inclusion of a detailed "System Faults" troubleshooting table is an invaluable maintenance feature. It allows technicians to quickly diagnose common problems related to the refrigerant circuit, electrical components, and defrost cycle, facilitating efficient repairs and minimizing downtime. This table helps identify primary and secondary causes, guiding maintenance personnel directly to potential solutions.
  • Documentation: The instruction to record system information, pressures, and temperatures after charging provides a baseline for future maintenance and troubleshooting. This documentation helps track the system's performance over time and identify deviations that may indicate a problem.
  • Component Protection: Recommendations such as wrapping wet rags around valve bodies during brazing and avoiding direct flame on the basepan protect sensitive components from heat damage, extending their operational life.
  • AHRI Certification: The mention of AHRI certification signifies that the unit, when installed as part of a complete system, meets industry performance standards, which often correlates with better reliability and reduced maintenance needs over time.

In summary, the Trane Condensing Units (4TTX8 series) are designed for efficient cooling, and this installer's guide provides comprehensive instructions to ensure a safe, compliant, and high-performing installation, laying the groundwork for reliable operation and simplified maintenance throughout the unit's service life.

Trane 4TTX8048A Specifications

General IconGeneral
Model4TTX8048A
TypeAir Conditioner
SEER Rating18
RefrigerantR-410A
Voltage208/230 V
Phase1
Sound Level (Outdoor Unit)74 dB
Cooling Capacity48, 000 BTU/H
Compressor TypeScroll

Related product manuals