CVHE-SVX02M-EN
A–1
Appendix A. Forms and Check Sheets
The following forms and check sheets are included for
use with Trane start-up of CVHE, CVHF, and CVHG
CenTraVac™ chillers. Forms and check sheets are used,
as appropriate, for installation completion verification
before Trane start-up is scheduled, and for reference
during the Trane start-up.
Where the form or check sheet also exists outside of
this publication as standalone literature, the literature
order number is also listed.
“CenTraVac™ Chiller Installation Completion and
Request for Trane Service,” p. B–1 (CTV-ADF001*-
EN)
“CVHE, CVHF, and CVHG CenTraVac™ Chiller Start-
up Tasks to be Performed by Trane,” p. C–1
“CVHE, CVHF, and CVHG CenTraVac™ Chiller
Annual Inspection List,” p. D–1
“CVHE, CVHF, and CVHG CenTraVac™ Chiller
Operator Log,” p. E–1
Unit Start-up/
Commissioning
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up.