Startup
RRU-SVX01F-EN 41
enter lockout with all outputs off. Reset is accomplished by
cycling the power off for a minimum of 5 seconds.
High Fire Test Following Normal Burner Starting
Sequence
At ROD override, Heating Control Signal to
100 percent.
When pressure at PG2 stabilizes, confirm PG1 and
PG2 pressures are within ±5 percent of the
pressures shown on Burner Data Plate.
Record Gas Pressures
PG1
PG2
At ROD, read and record
Outdoor Air Temperature
Discharge Air Temperature
Burner P
Release Heating Control Signal Override
Low Fire Test Following Normal Burner Starting
Sequence
Override Heating Control Signal to 0 percent
Confirm PG1 and PG2 pressures are within
±5 percent of the pressures shown on Burner Data
Plate
Allow a minimum of 5 minutes of operation at
0 percent heating signal
At ROD read and record
Outdoor Air Temperature
Discharge Air Temperature
Burner P
Record Gas Pressures
PG1
PG2
Ignition Cycle Test
Release Heating Control Signal Override
Complete at least (5) calls for heat
At each call for heat default heating startup,
signal is 25 percent
Following each ignition test and before
attempting the next test monitor, analogue
Heating Control Signal at ROD to be sure heat
signal is released at end of each 90-second
warm-up period
WARNING
Hazard of Explosion!
Failed gas components could explode or leak
flammable gas which could cause a fire resulting in
death or serious injury or property damage. To avoid
damage to unit if PG1 or PG2 exceed data plate
pressures +5 percent, disable incoming gas using the
manual shutoff valves and ensure incoming pressure is
within nameplate data BEFORE enabling the gas.