TC 2020R Installation
TR22.1 2020 Installation with SMC_July_03
2
1. Check power: 460V, 480V, Wye-configuration (Y) as required according
to the pre-installation manual.
2. Check to make sure clean, dry air is supplied to the machine.
3. Make sure there is at least 40 gallons of Mobile DTE25 oil on-site.
4. Inventory all the parts that came with the machine and inspect the parts
for damage. If the parts are damaged, record the damage, take
pictures, and call TRUMPF Service department 860-678-8584.
5. Verify machine options according to the list.
6. Inspect the installation area, making sure there is adequate room. Make
sure there are no cracks between the support feet of the machine.
Check floor for proper thickness and level.
7. Make sure there is sufficient test tooling (at least 2 cartridges).

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trumpf TC 2020R and is the answer not in the manual?

Trumpf TC 2020R Specifications

General IconGeneral
BrandTrumpf
ModelTC 2020R
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals