Document No: LT0255 F3200/NDU AS4428.1 Installation Manual
Installation & Wiring
Issue 1.04 30 June 2004 Page 5-19
Notes
1. Wire an in-line fuse holder with 6A fuse from Batt+.
2. The Bell Monitor must be Rev 3 or greater and is supplied with instructions, adhesive
based stand-offs, and EOLRs.
FIGURE 5.5.6
USING BELL MONITOR BOARD ON ANCIL 3/BELLS RELAY
FIGURE 5.5.7
WIRING T-GEN TO F3200 BELLS/ANC 3 RELAY
2k5
ELD
56k
DUAL LINE 50W MAX TOTAL
T-GEN 50
Master
+24V
+24V +
0V
0V Line
LM- -
SIG
NO Fault
COM
T-GEN 50
Slave
+24V
+24V +
0V
0V Line
SIG -
NO Fault
COM
+24V
0V
BELLS
-/C
SINGLE LINE 50W MAX
(See Note 2)
ELD
100k
ELD
100k
(See Note 2)
(See Note 2)
F3200
MAF
See
Text
Batt +
NO
NC
BELLS +
0V
EOLR
+V
Evac
0V
Anc 3
Evac
-
EOLR
Bell Monitor
Rev 3
Up to 3 branches of
Load.
Evac +
2K7
6Adc
Fuse
Ext Def -
BELLS -
Lk2
Lk3
Lk4
F3200