1. INSPECTING AND PREPARING THE HEATER
Remove the cardboard box, which comes packaged with the heater.
It should contain the following: Thermostat, temperature and pressure
relief valve, brass “Tee fitting, insulation, lid, and screws.
Do not cover the temperature and pressure relief valve opening.
2. LOCATION
Solid foundation and dry location.
Protect heater water lines from freezing.
Area free of flammable vapors.
Sufficient room to service heater.
Not in close proximity to wood burning stove.
Where leak will not damage property.
3. PROTECTION FROM WATER DAMAGE
Be sure to make provisions to protect the area from water damage if
a leak should occur in the tank or connected fittings.
4. TEMPERATURE AND PRESSURE RELIEF VALVE
WARNING: Improper installation will present potential hazard to
life and property.
A temperature and pressure relief valve with an 8-inch stem should
be used.
Check to be sure that proper temperature and pressure relief valve
requirements are met.
Temperature and pressure relief valve installed as shown in
INSTALLATION DIAGRAM 1 on page 20 and INSTALLATION
DIAGRAM 2 on page 20.
The 3/4" discharge pipe is properly protected from freezing and
restrictions.
No valve between tank and the temperature and pressure relief valve
or in drain line.
Provision for hot water discharge from the temperature and pressure
relief valve.
5. BOILER SUPPLY CONNECTIONS
Return line (back to the boiler) connected to the “HX Out” fitting.
Supply line (from the boiler) connected to the “HX In” fitting.