General instructions
pfu basic range: Prefabricated concrete
enclosure, ground-level walk-in type
Installation
8. Installation
When installing the pfu at its location, it is essential to follow
current legislation on electrical installations in networks,
including both local regulations and the specications
of the utility company. The instructions included in this
document must be followed during electrical installation.
The site must be visited in advance to check if vehicles can
have access and if there is sucient space for the unloading
and assembly operations, taking into account the distances
to overhead lines, slopes, etc.
8.1. Receiving the equipment
Upon receipt of the building, carefully check the following:
1. The general condition of the assembly.
2. Absence of bangs or breakage, especially at the
connection points to other items or close to the DEHA
couplings.
3. The state of the paintwork, checking for the absence of
chipping, scratches, etc.
4. Accessories: If damage or absences are observed,
immediately inform the transport agent and Ormazabal.
8.2. Location
The site location should be precisely dened, indicating the
levels of alignment and height of the possible reference
points, such as: roads, kerbs, milestones, fences, pavilions,
pylons, etc.
Incorrect levelling may cause the base of the body to
break.