b) Anchor Crossover Assembly
Remove Anchor Crossovers from service if inspection indicates the
following damage:
1) Excessive rust or corrosion prevents the crossover
from operating properly.
2) Excessive wear on the OD or ID of crossover.
3) Any damage to integral female threads that would
prevent proper installation.
c) Anchor-“C”-type & “D”-type Shackles – Remove shackles from
service if inspection indicates the following damage:
1) Visible signs of damage or galling on screw threads
that would prevent proper operation.
2) The metal shackles show excessive wear.
3) The shackles screw pin is damaged and cannot be
fully installed into the mating threads.