39
THIRD
Install the SPM
®
FSR main line Spines next. These Spines should
be threaded through the Ribs already installed on the flow line.
See pages 23-25 of this guide for reference.
TIP - It is recommended to start at one end and work
toward the other end.
TIP - Installers should remember to twist SPM
®
FSR Ribs
prior to installing the SPM
®
FSR Spine main line through.
This helps ensure a tight installation
FOURTH
Install the SPM
®
FSR anchor line Spines. See pages 31-33 of this
guide for reference.
INSPECTION
In order to ensure the continued safe operation of the SPM
®
Flow
Line Safety Restraint System, Weir Oil & Gas requires annual
SPM
®
FSR inspection. Inspection of SPM
®
FSR components
must be performed by a Weir Oil & Gas technicians. Contact
your Weir Oil & Gas sales representative at 1-800-342-7458 to
schedule the annual inspection.
The primary mode of inspection is a visual inspection according
to SPM
®
Flow Line Safety Restraint Annual Inspection Procedure.
Proof Load Testing is also offered by Weir Oil & Gas. This testing
requires multiple samples to be destroyed by pull-test. Though not
mandatory, this testing offers an additional level of reassurance.
*Identification tags must be punched or marked with the date the
inspection was performed.
Reference Documents for Annual SPM
®
FSR Inspection:
Weir Oil & Gas Engineering Bulletin 1024
This bulletin briefly explains the annual SPM
®
FSR procedure and
details which documentation is required.