Page #134 background imageLoading...
Page #134 background image
6-4
SM-16005-rev.2
FIELD WORK INSTRUCTIONS
6.3 Maintenance Work
(1) For Outdoor Unit and Indoor Unit
(a) Fan and Fan Motor
Lubrication - All fan motors are pre-lubricated and sealed at the factory. Therefore, no
lubricating maintenance is required.
Sound and Vibration - Inspect for abnormal sounds or vibration.
Rotation - Check that the fan rotates counterclockwise and inspect the rotating speed.
Insulation - Inspect for electrical insulation resistance.
(b) Heat Exchanger
Clogging - Inspect for any accumulated dirt and dust and remove any at regular intervals. As for
an outdoor unit, other obstacles such as growing grass and pieces of paper, which might interrupt
air ow, should also be removed.
(c) Piping Connection
Leakage - Inspect for refrigerant leakage at piping connections.
(d) Cabinet
Stain and Lubricant - Inspect for any stain or lubricant and remove it, if any.
Securing Screw - Inspect for loose or missing screws and secure or replace as required.
Insulation - Inspect for peeling thermal insulation material on the cabinet and repair it, if any.
(e) Electrical Equipment
Activation - Inspect for abnormal activation of the magnetic contactor, auxiliary relay, or printed
circuit board (PCB).
Line Condition - Pay attention to working voltage, amperage and phase balance.
Inspect for faulty contact caused by loosened terminal connections, oxidized contacts, foreign
matter, and other items. Inspect for electrical insulation resistance.
(f) Control and Protective Devices
Setting - Do not readjust the setting in the eld.
(2) For Outdoor Unit Only
(a) Compressor
Sound and Vibration - Inspect for abnormal sounds or vibration.
Activation - Check that the voltage drop of the power supply line is within 16% at start and within
2% during operation.
(b) Reversing Valve
Activation - Inspect for any abnormal activating sound.
(c) Strainer
Clogging - Check that there is no temperature difference between the ends.
(d) Ground Wiring
Ground Line - Inspect for continuity to the earth ground.
(e) Crankcase Heater
Activation - Apply power to the outdoor unit(s) at least 12 hours prior to operation of the system
for preheating of the compressor oil.
(3) For Indoor Unit Only
(a) Air Filter
Cleaning - Inspect for, and remove, any accumulated dirt and dust and remove according to the
“Engineering Manual”.
(b) Condensate Pan, Drain-up Mechanism and Condensate Pipe
Condensate Line - Inspect and clean the condensate line at least twice a year.
Drain-up Mechanism - Inspect for activation of drain-up mechanism.
(c) Float Switch
Activation - Inspect for activation of oat switch.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the York IDM030B21E Series and is the answer not in the manual?

York IDM030B21E Series Specifications

General IconGeneral
BrandYork
ModelIDM030B21E Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals