ABB | SACE Emax 2
Ekip Touch - Protections
9 - Additional protections and functions
92 | © 2023 ABB | 1SDH001330R1002 - ECN000297030
Synchrocheck
With regard to closing the interconnection switch, the
Ekip Synchrocheck
module recognizes and
reports whether there are synchronism conditions between two independent voltage sources (example:
generator + grid).
A description of the module, the protection function and performance is given in the chapter dedicated
to the modules (page 247).
Programmable Functions and
Commands
Eight commands are available, with activation that can be programmed on the basis of signals or events.
Distributed among different Ekip Touch menus, the commands are:
Name Description Path (page)
External Trip Sends a TRIP command
Advanced
-
Functions
(47)
Trip RESET Reset of the trip signal
Turn on SET B Changes the protections set, from Set A to Set B
2I Mode
It activates 2I protection, if configured for this
function
Advanced
-
Functions
-
2I Menu
(62)
RESET Energy Resets the energy meters
Measurements
-
Energy
(48)
YO Command Sends an open command
Settings
-
Functions
(
49)
YC Command Sends a close command
(1)
LOCAL Switch On
Changes the configuration, from Remote to
Local
Settings
-
Modules
-
Functions
(49)
Signaling RESET Reset the contacts of the signalling modules
(1)
the MOE-E storage command must be present
Parameters
Each command provides two programming parameters:
Parameter Description Default
Function
Event or several command activation events (up to eight, in AND
or OR logic configuration). The Custom configuration can be
programmed via Ekip Connect.
Deactivated
Delay
This is the minimum time the expected event must be present in
order to activate the command; the value is given in seconds and
can be set within a range: 0 s to 100 s, in 0.1 s steps
0 s
IMPORTANT: the commands are sent if all the operating conditions expected by the unit
are present (connections, power supplies, alarms, etc.)