EasyManua.ls Logo

ABB SACE Emax E4.2-A User Manual

ABB SACE Emax E4.2-A
77 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
DOC. N° 1SDH001000R0002 - ECN000109166 - Rev. D
SACE Emax 2
Emax low voltage air circuit-breakers Emax E2.2-E4.2-E6.2
Installation, operation and maintenance instructions for
the installer and the user
Question and Answer IconNeed help?

Do you have a question about the ABB SACE Emax E4.2-A and is the answer not in the manual?

ABB SACE Emax E4.2-A Specifications

General IconGeneral
Rated VoltageUp to 690 V AC
StandardsIEC 60947-2
TypeAir Circuit Breaker (ACB)
Trip UnitElectronic
MountingFixed or withdrawable
Poles3 or 4 poles
Protection FunctionsShort-circuit, Earth fault
CommunicationModbus, Profibus

Summary

2 - Safety Precautions

General and Specific Warnings

General and specific warnings for safe installation and operation.

Management Operations

1 - Transport and Checking on Receipt

Instructions for safe transport and checking of delivered circuit-breakers.

2 - Unpacking and Handling Procedures

Opening the Packaging

Step-by-step guide for safely opening the packaging.

3 - Description of SACE Emax 2

Circuit-breaker Structure and Types

Overview of circuit-breaker structure and types (fixed/withdrawable).

Manual Operations for Circuit-Breaker

Opening and Closing Operations

Step-by-step guide for manual opening and closing operations.

Racking-in and Racking-out Operations

Racking-in/Racking-out Procedures

Procedure for inserting the moving part into the fixed part.

Racking-in/Racking-out Procedures (Continued)

Continuation of racking-in procedures, including crank operations.

Ekip Dip Trip Unit

4 - Protections

Protection Operating Principle and L Protection

How protections activate and details on overload protection (L).

S Protection Details

Details on selective short circuit protection (S).

I Protection Details

Details on instantaneous short circuit protection (I).

G Protection Details

Details on ground fault protection (G).

5 - Measurements

6 - Test Procedures

7 - List of Alarms and Signals

Putting into Service and Maintenance

1 - Putting into Service

General checks and procedures for putting the circuit-breaker into service.

2 - Identification of Alarms or Failures

Alarms and Failures Identification

Identifying faults, causes, and remedies using LEDs or display.

Faults, Causes, and Remedies

Lists faults, their causes, and suggestions for resolution.

3 - Maintenance Procedures

Maintenance Safety and Personnel Requirements

Safety warnings for maintenance and definition of skilled personnel.

4 - First Level Maintenance

5 - Second Level Maintenance

6 - Decommissioning and Treatment at End of Life

Safety, Personnel, and Material Treatment

Safety rules, personnel roles, and material treatment for decommissioning.