Mothballing the turbocharger
10
Taking the engine out of operation for
up to 12 months
10.1
Page 112
September 2014 HZTL2498_EN Revision A
The rotor and bearing parts must be dismantled and subsequently
refitted by an ABB Turbocharging Service Station
Clean all parts
Coat plain surfaces of steel and cast parts with anticorrosive oil
Fit turbocharger completely.
Rotation of the rotor in the stack draught
If the rotor turns as a result of the stack draught:
Install a blind flange between the outlet flange of the compressor
casing and the charge air duct.