Installation and Commissioning Guide - Standard Commercial Split Ducted Commercial Outdoor Unit
Doc. No.0525-056 Ver. 7 220308
Installation and Commissioning Guide
Split Ducted Outdoor Units
2
Table of Contents
. Introduction ..............................................................................................................................
. Information About This Guide
. Product Inspections
. Codes, Regulations And Standards
. Important Safety Symbols And Labels
. General Information ..................................................................................................................
. Safety Instructions ....................................................................................................................
. Installation Information ............................................................................................................
. Operation Manual Access ..........................................................................................................
. Components Overview ..............................................................................................................
. Unit Dimensions, Clearances and Weights .................................................................................
. Unit Dimensions
. Minimum Service Access Area, Airflow Clearances and Weights
. Banking of Units ......................................................................................................................
. Unit Lifting Procedure .............................................................................................................
. Outdoor Unit Preparation ........................................................................................................
. Field Pipe Connection ..............................................................................................................
. Piping and Brazing
. Pressure Testing
. Evacuation Procedure (Triple Evacuation)
. Electrical Installation ...............................................................................................................
. Split Unit Electrical Connection ...............................................................................................
. Control Cable Length and Specification ...................................................................................
. Refrigerant Charging ...............................................................................................................
. Maintenance ...........................................................................................................................
. Maintenance Frequency Checklist ...........................................................................................
. Key Parts List ...........................................................................................................................
. Start Up and Commissioning Report ........................................................................................