31
Results Manager
Job Creation in the Results Manager
Note: See “New Job Creation” on page 15
for a simplied means of creating New Jobs.
1. From the Results Manager page, use arrows
to highlight the desired Drive where test results
will be saved.
2. Press the Tools soft key to display the Tools menu
(Tools menus will vary depending on the selected
level in the le tree structure as shown in “Tools
Menus in the File Tree Structure” on page 28).
3. Use arrows to highlight the New Job option
and press key to display the Text Editor (see
“Text Editor” on page 65 for details on how
to use it). Enter a name for the New Job. Press
OK to return to the Results Manager page.
4. With the created New Job highlighted, press
Tools > New Route. The Route page will be
displayed.
5. Use arrows to highlight ‘End 1...’ or ‘End 2...’.
6. Press Enter key to display the End Locations
sub-page.
7. To create new End Location(s), press the New
soft key. Using the displayed Text Editor, create
new End name. Press OK.
8. Create as many End Names as needed for a Job
and press key to return to the Route page.
9. From Route page, use arrows to select Ends
for the Route. Press OK.
10. With the created Route highlighted, press Tools
>New Cable.
11. Using the displayed Text Editor, enter a name for
the new Cable. Press OK.
If needed, create more Jobs, Routes, Cables.
12. With the Cable to be tested in the desired job
selected, press Main Menu .
13. Select a Test mode to begin testing bers in
the selected Cable. Before pressing Test, verify
test setup on the Job Settings page within the
selected Test mode.
END LOCATIONS SUB-PAGE
NEW ROUTE CREATED
ROUTE PAGE