Final installation checks
Before leaving the installation site, check the following:
...................................................................................................................................................................................................
1
Secure all cables along their routes.
...................................................................................................................................................................................................
2
Verify that all the exterior conduit and cable connections are secure.
...................................................................................................................................................................................................
3
Inspect the site for loose tools, materials, and parts. Remove all such loose tools,
materials, and parts.