GRID
High Voltage Switchgear
PS 0009EN
04 1996-03-18 2011-03-21 2 / 2
Sheet N° Revision 1st issue Revision date Page
SAFETY INSTRUCTIONS
PACKING
TRANSPORT
INSTALLATION
START-UP
OPERATION
MAINTENANCE
SCRAPPING &
RECYCLING
Identify the equipment to be worked on and ensure it
is switched off.
X X X
Obtain as much information as possible from the user
regarding the condition of the unit.
X X X
Check that the unit is earthed both upstream and
downstream.
X X X
Demarcate the work area.
X X X
Ensure that the operator is equipped with the personal
protective clothes and equipment required (safety
glasses, gloves, safety boots, harness, etc.).
X X X
Ensure that the equipment used is compliant and in
good condition (scaffolding, slings, suspended
platforms, electrical equipment, tools, etc.).
X X X
Ensure that the safety instructions in respect of each
particular hazard are complied with.
X X X