Installation
Filling with SF
6
gas
P32--0001EN/03
3/8
07--2012
© ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be
relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is
strictly prohibited.
GRID
Confirming the pressure
Instructions
The following table gives the steps for confirming the filling pressure of
SF
6
gas:
Step Action Remark/Illustration
1 Disconnect the reducing valve
tube (10), from the filling toom
(2).
NOTE
: Keep the end of the
disconnected tube (10) in a
high position to keep the SF
6
inside and avoid entry of
humid air .
2
10
2 S Connect the pressure gauge
0...1 MPa (14) pipe (15) to the
filling tool (2).
S When the desired pressure is
confirmed, remove the pressure
gauge (14) and store it away
from humidity.
14
15
2
3 Remove the filling toom (2) and
replace the cap (17) (4 daN.m).
2
17