TD 92356GB
2007-03-16/ Ver. C
Installation Guide
PCR Charging Rack
3
3 Installation
The units should be placed in a dry environment with a temperature range of
0 to +40º C.
Avoid mounting the Charging Rack where the coverage is not sufficient. This can
reduce the messaging capacity.
The PCR Charging Rack module must be mounted according to the label. See figure 6
on page 7.
The units should be mounted on concrete or plaster walls only.
Delivery includes:
One Inlet accessory kit including;
Cable supports and screws
Rectangular assembly covers
Clips (only used for Power Supply module)
A modular cable is included in the delivery of Extension PCR-E for connection to or from
another Extension PCR-E or Master PCR-M.
Required tools and material:
Three-wired cable for the mains power with diameter 4-8.5 mm. Make sure that the
used cable is grounded and approved for the current and voltage in question.
Screwdrivers
Cutting pliers
Multimeter
Screws and wall plugs for wall mounting. Make sure the screws and wall plugs are
correct for the type of wall used. See example below.
Wall material Wall plug Screw diameter
Single plasterboard Thorsman TP1 3.5-5 mm
Double plasterboard Thorsman TP2 3.5-5 mm
Concrete Thorsman TP2 3.5-5 mm