Example of transport fixations
Also remove the 2 extra fixation bolts (7) on the roof.
5. Check the oil level: the level should be between the 2 lines on the sight-glass (SG). Add oil
via the filler plug (FC) if necessary. See Oil specifications for details about the oil to be used.
Detail of crankcase with oil filler plug (FC) and sight glass (SG)
6. Check that the electrical connections correspond to the local codes. The installation must be
earthed and protected by fuses in all phases. An isolating switch must be provided.
7. Check the connections at the primary side of transformer (T1). See the Electrical Diagram in
Electrical connections.
On air-cooled compressors, check the settings of the cooling fan circuit breaker (Q15) and
overload relay (F21).
8. Close all manual drain valves of the condensate traps.
9. Check the storage instructions for VSD compressors (9820 4681 00) regarding start-up after
a long period of storage. See also Storage instructions after installation.
Instruction book