SP-7XE/F Full-Rise Scissor Lift 21 P/N 5900010Rev. B3 — September 2023
Not all components shown. There must be 4.25 inches of Concrete below the bottom of the
Concrete Cutouts. In this drawing, the Console would be on the left.
The Flush-Mount Lift settings for the SP-7XEF are:
Length. The Length of each SP-7XEF Frame Base is 106 inches / 2,692 mm; make the cutout
1 in. / 25 mm longer to get 107 inches / 2,718 mm.
Width. The Width of each SP-7XEF Frame Base is 22 inches / 559 mm; make the cutout
1 in. / 25 mm wider to get 23 inches / 584 mm.
Depth. The Lowered height of each SP-7XEF Frame is 6.4 inches / 163 mm. Do not add an
extra inch to this value.
Distance Between. The two SP-7XEF Bases can be from 38 to 44 inches / 965 to 1,118
mm apart. You do not add an extra inch to this value.
Important: If you are installing the SP-7XEF over a pit, do not set the Distance Between to
the width of the pit if the width of the pit is less than 38 inches or more than 44 inches. The two
Bases must be from 38 to 44 inches apart, even if installed over a Service Pit.
Distance to the Console. The supplied Hydraulic Hoses allow the Console to be up to
40 inches / 1016 mm from the nearest Base. Do not add an extra inch to this value.
CAUTION If you create your Concrete Cutouts and then change your mind about the Distance
Between or find out you made a mistake with one of the dimensions, it is very difficult
to fix. BendPak strongly recommends checking your plans several
times before cutting and pouring your Concrete Cutouts.