Installation 3.5 Commissioning
Page 34 BOGE Operating instructions for C 16 N...C 30 N, C 16 F N...C 30 F N series screw compressors
Checking installation
requirements
Checking the rotational
direction
Changing the rotational direction
WARNING!
Make sure that the compressor is installed according to the installation
requirements!
Prior to starting the compressor for the first time, check if the transport secur-
ing device was duly removed and the GM belt tensioning device activated
(see chapter „3.3 Installation“)!
Record the test results in the commissioning certificate.
WARNING!
Always check the rotational direction of the drive motor prior to commission-
ing/initial start up.
Even brief operation in the wrong direction of rotation (more than approx.
5 seconds) may cause significant damage to the air end!
Record the test results in the commissioning certificate.
WARNING!
Ensure that the rotational direction coincides with the rotational direction
arrow on the air end.
Close mains disconnecting device.
Switch the compressor on and immediately off again to check the rota-
tional direction.
WARNING: Risk of injury!
Actuate emergency-stop switch/button, open mains disconnecting device
and secure by means of lock out tag out.
Interchange two phases (L1, L2 or L3) in the power cable.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Boge C 20 F N and is the answer not in the manual?

Boge C 20 F N Specifications

General IconGeneral
BrandBoge
ModelC 20 F N
CategoryAir Compressor
LanguageEnglish

Related product manuals