SSB 6720866942 (2018/06) US
Installation | 13
4.2.2 Setting the Unit
Remove the top and side carboard panels and the plastic lm. Lift the
unit off the shipping skid with a forklift and position it on the oor in the
desired location.
WARNING: When lifting or moving the boiler: do not attempt
to manipulate the boiler using the top corner tripods or any
other component of the boiler.
WARNING: When lifting or moving the boiler with a forklift:
make sure the forks are longer than the boiler size (width or
depth) so that forks stick out as per Fig. 8.
Fig. 8 SSB 800 SA, 1000 SA and 1000 TL Forklift Handling
WARNING: Always keep the boiler in the upright position.
If a crane is required, the boiler must be lifted through bands.
WARNING: When lifting the boiler with crane: use bands,
no chains. Bands must comply with federal, state and local
rules.
WARNING: When lifting the boiler with crane: the bands
must be positioned according to the Fig. 9.
In multiple unit installations, it is important to plan the position of each unit
in advance. Sufcient space for piping connections and future service/
maintenance requirements must also be taken into consideration. All
piping must include ample provisions for expansion.
4”
4”
Fig. 9 SSB 800 SA, 1000 SA and 1000 TL Crane Lifting Handling
The unit must be installed on a concrete at oor, with no gradient in any
direction, to ensure proper condensate and water drainage (see Fig. 10).