START-UP CHECKLIST
(REMOVE AND STORE IN JOB FILE)
I. PRELIMINARY INFORMATION
MODEL NO: .............................................................................................................................................................
SERIAL NO: ..............................................................................................................................................................
DATE: ........................................................................................................................................................................
TECHNICIAN: ...........................................................................................................................................................
JOB LOCATION: ...........................................................................................................................................................
II. PRE-START-UP (insert checkmark in box as each item is completed)
____ VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
____ VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
____ CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
____ CHECK GAS PIPING FOR LEAKS
____ CHECK THAT INDOOR (EVAPORATOR) AIR FILTER IS CLEAN AND IN PLACE
____ VERIFY THAT UNIT INSTALLATION IS LEVEL
____ CHECK FAN WHEEL PROPELLER FOR LOCATION IN HOUSING ORIFICE AND SETSCREW TIGHTNESS
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE L1-L2 __________ L2-L3 __________ L3-L1 __________
COMPRESSOR AMPS L1 __________ L2 __________ L3 __________
COMPRESSOR AMPS L1 __________ L2 __________ L3 __________
INDOOR (EVAPORATOR) FAN AMPS __________
TEMPERATURES
OUTDOOR (CONDENSER) AIR TEMPERATURE: __________ DB
RETURN-AIR TEMPERATURE: __________ DB __________ WB
COOLING SUPPLY AIR: __________ DB __________ WB
GAS HEAT SUPPLY AIR: __________
PRESSURES
GAS INLET PRESSURE __________ IN. WG
GAS MANIFOLD PRESSURE__________ IN. WG
REFRIGERANT SUCTION __________ PSIG SUCTION LINE TEMP*__________
REFRIGERANT DISCHARGE __________ PSIG DISCHARGE LINE TEMP† __________
____ VERIFY REFRIGERANT CHARGE USING CHARGING TABLES
____ VERIFY THAT 3-PHASE SCROLL COMPRESSOR (582A048 and 583A030-060) IS ROTATING IN CORRECT DI-
RECTION.
* Measured at suction inlet to compressor
Measured at liquid line leaving condenser