Chapter 1 Install the Shelf and Backplane Cable
NTP- A13 Perform the Shelf Installation Acceptance Test
Figure 1-13 Installing the Rear Cover with Standoffs
Stop. You have completed this procedure.
NTP-A13 Perform the Shelf Installation Acceptance Test
Warning
The covers are an integral part of the safety design of the product. Do not operate the unit without the
covers installed.
Step 1 Complete Table 1-5 by verifying that each applicable procedure was completed.
Purpose Use this procedure to perform a shelf installation acceptance test.
Tools/Equipment Voltmeter
Prerequisite Procedures Applicable procedures in Chapter 1
Required/As Needed Required
Onsite/Remote Onsite
Security Level None