Chapter 1 Install the Shelf and Backplane Cable
NTP- A13 Perform the Shelf Installation Acceptance Test
Step 2 Complete the “DLP-A32 Inspect the Shelf Installation and Connections” task on page 17-39.
Step 3 Complete the “DLP-A33 Measure Voltage” task on page 17-39.
Step 4 Continue with Chapter 2, “Install Cards and Fiber-Optic Cable.
Stop. You have completed this procedure.
Table 1-5 Shelf Installation Task Summary
Description Completed
NTP-A1 Unpack and Inspect the ONS 15454 Shelf Assembly, page 1-4
NTP-A2 Install the Shelf Assembly, page 1-5
NTP-A3 Open and Remove the Front Door, page 1-6
NTP-A4 Remove the Backplane Covers, page 1-7
NTP-A5 Install the EIAs, page 1-8
NTP-A6 Install the Power and Ground, page 1-9
NTP-A7 Install the Fan-Tray Assembly, page 1-11
NTP-A119 Install the Alarm Expansion Panel, page 1-13
NTP-A8 Attach Wires to Alarm, Timing, LAN, and Craft Pin Connections,
page 1-16
NTP-A120 Install an External Wire-Wrap Panel to the AEP, page 1-17
NTP-A9 Install the Electrical Card Cables on the Backplane, page 1-22
NTP-A10 Route Electrical Cables, page 1-23