Prometha™ Installation
750-441
2
Wire stripper
Container for drill shavings
Lockout/Tagout kit
Portable monitor (MiniDisplayPort compatible)
Display adapter cable (monitor port to Mini DisplayPort)
Recommended:
Cable tie installation tool
Optional:
RF signal meter (5 band)
Torpedo level (for antenna placement)
Network cable tester
3 - Installation Options:
Each gateway device can accommodate any combination of up to 8 of the compatible systems listed
above. There are several installation location options for the gateway hardware. Regardless of the
option chosen, the installation must ensure that gateway power and Hawk network connections are
maintained as long as any connected boiler is powered up. An optional 5- or 8-port Ethernet switch
will need to be added for systems with no available Ethernet ports.
Single Boiler Installation Options
• Hawk Panel
• PT Panel
• DT Panel w/o Ethernet Switch
Multiple Boiler Installation Options
• Master Panel
• PT Panel
• DT Panel w/ Ethernet Switch
The Hawk Panel option uses the existing Hawk control panel to house the Prometha™ hardware.
The Master Panel and PT (Protocol Translator) Panel options use an existing Master Panel or stand-
alone ProtoNode/CB-PT panel to house the Prometha™ components; the existing Ethernet switch
provides the connection point for each Hawk network device.
The DT (Data Transfer) Panel option incorporates all of the Prometha™ hardware in a single stand-
alone panel and is available with or without an Ethernet switch.
Note: If a site has a weak cellular signal at the Hawk equipment location (as determined during the
pre-installation sales process), the DT Panel can be located up to 328 ft. away from Hawk network.