3
Section 2 Installation
2C. Mounting
2C-1.FloorMounting
The DEL AOP 50 is shipped with the Mounting Feet installed in the
oor mounting position. Adjust the position of the feet if necessary
and tighten the screws. Mount the DEL AOP 50 to the equipment pad
through the slots provided in the feet using appropriate hardware for
the mounting surface.
2C-2.WallMounting
The DEL AOP 50 unit does not have holes for wall mounting but can
be mounted on the wall if desired.
1. Drill 4 holes, (.257 in, drill size F), in the back of the enclosure
approximately as shown in Figure 2.
2. Open door as described in SECTION 4C-1 and clean out debris.
3. Install Mounting Feet in drilled holes with hardware provided.
4. Mount unit to wall through the slots in the Feet using appropriate
hardware for the mounting surface.
2D.Electrical
2D-1.MainPower
Connect the DEL AOP 50 to the pool timing clock so that the DEL AOP
50 operates simultaneously with the pool pump. The DEL AOP 50 has
four available Knockouts for a 1/2” conduit tting, two on the back and
one on each side. Remove only the ideal Knockout for the installation
and install the proper conduit tting. Remove the Cover (Refer to
SECTION 4C-1) and locate the Terminal Block (Refer to Figure 5) on
the left side of the enclosure. Connect Line 1, Line 2, and Ground to
the Terminal Block as indicated by the label on the Generator Bracket.
Refer to the IMPORTANT SAFETY INSTRUCTIONS at the beginning
of this manual for important wiring information.
2D-2. Grounding Lug
Using a solid copper conductor, connect to the Grounding Lug on the
left side of the DEL AOP 50 to an appropriate earth contact.