B
Rev
RE
Status
Model Version
04
01
Version
01
A
Status
Rev
7 of 14
page
Bulletin
AE01B-A0599-001
Installation Instructions
MT050C
FOUR AIR
OUTPUT PORTS
2.4 - Mechanical Installation
Once the electrical connections are completed, turn on the dehydrator to verify that it turns on and has air flow at the air
output ports. The dehydrator needs to run without being connected to a closed air volume for at least 45 minutes prior to
connection to the transmission lines. Before connecting the dehydrator to the transmission lines, verify the pressure rating of
the transmission system.
Every dehydrator comes with the required accessories for standard installations. The dehydrator installation kit includes
the following components.
North American Power Cord (x1)
•
International Power Cord (x1)
•
1/8" NPT Straight Connector for 3/8" PE Tubing (x4)
•
Right Angle M/F 1/8" NPT Fitting (x4)
•
#10-32 Screws (For standard rack installation) (x4)
•
PTFE Tape (1 roll)
•
PE Tubing (100 feet, 30.5 m)
•
The dehydrator comes with 100 feet (30.5 m) of polyethylene (PE) tubing. If all four output ports are being used, there is 25 feet
(7.6 m) of tubing available per port. Additional tubing is available in the following kits.
AE01K-D0840-025 - 25 foot (7.6 m) PE tubing bundle
•
AE01K-D0840-050 - 50 foot (15.2 m) PE tubing bundle
•
AE01K-D0840-100 - 100 foot (30.5 m) PE tubing bundle
•
AE01K-D0840-132 - 132 foot (40 m) PE tubing bundle
•
AE01K-D0840-500 - 500 foot (152.5 m) PE tubing bundle
•
The fittings included in the installation kit are designed to work with this tubing. The included fittings will attach to the
waveguide pressure ports and the tubing shall be run between these fittings and the dehydrator output ports. In addition to the
power cord, grounding wiring and output ports connections, the alarm terminals should be wired either NO or NC per the details
in section 1.4. The transmission lines must be purged of any latent moisture in them. The following section details the
procedure for properly purging the system.