Half Recessed Installation
1. This installation is optimized for a 2x4 framed
wall. Prepare the framed opening according to the
height and width of the chart on page 7. Provide
an electrical outlet on the back side of the framed
opening, near the top right corner.
2. Install L Metal Nailing Flanges.
3. Install the re unit in the framed opening with a
minimum 1 ¼ drywall screws to secure the unit.
4. Firebox must be covered with material of choice.
Mask the exposed re unit during this process.
Install drywall, tile or material of your choice to
the drywall stops on the perimeter of the re box.
For more information on the drywall stops see the
Product Guide on page 4. Decorate as desired.
5. Install the side and front glass pieces.