6.15 Commissioning
Prerequisites
To commission the units, the following steps must be carried out:
Prerequisite is correct mounting and correct electrical installation and, in the case of
wireless systems, correctly working radio links to all the auxiliary units
Make all plant-specifi c settings. Special attention must be paid to operating page
”Confi guration“.
For that purpose, the relevant operating level is to be selected as follows:
Press the OK button on the operator unit to switch to programming.
Press the Info button for at least 3 seconds and select operating level
“Commissioning“ with the setting knob. Then, press the OK button.
Make the functional check as described below
Reset the attenuated outside temperature
(operating page “Diagnostics of consumers“, operating line
“Outside temp attenuated“ (line 8703))
Functional check
To facilitate commissioning and fault tracing, the controller allows output and input
tests to be made. This allows to test the outputs and inputs. To make the tests, select
operating page “Input/output test“ and go through all available operating lines.
Operating state
The current operating state can be checked on operating page “State“.
Diagnostics
For detailed diagnostics of the plant, check operating pages “Diagnostics heat source“
and “Diagnostics consumer”.