11 | Commissioning
Installer reference guide
225
EPRA14~18D + ETVH/X16S18+23E
Daikin Altherma 3 H HT F
4P644737-1A – 2022.03
Typical workflow
Commissioning typically consists of the following stages:
1 Checking the "Checklist before commissioning".
2 Performing an air purge.
3 Performing a test run for the system.
4 If necessary, performing a test run for one or more actuators.
5 If necessary, performing an underfloor heating screed dryout.
11.2 Precautions when commissioning
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50hours before reaching smooth operation and
stable power consumption.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
11.3 Checklist before commissioning
1 After the installation of the unit, check the items listed below.
2 Close the unit.
3 Power up the unit.
You read the complete installation instructions, as described in the installer reference
guide.
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
The following field wiring has been carried out according to this document and the
applicable legislation:
Between the local supply panel and the outdoor unit
Between indoor unit and outdoor unit
Between the local supply panel and the indoor unit
Between the indoor unit and the valves (if applicable)
Between the indoor unit and the room thermostat (if applicable)
The system is properly earthed and the earth terminals are tightened.
The fuses or locally installed protection devices are installed according to this document,
and have NOT been bypassed.
The power supply voltage matches the voltage on the identification label of the unit.
There are NO loose connections or damaged electrical components in the switchbox.
There are NO damaged components or squeezed pipes on the inside of the indoor and
outdoor units.
Backup heater circuit breaker F1B (field supply) is turned ON.