5 Preparation
Installer reference guide
12
RZA200+250D7Y1B
Sky Air Advance-series
4P573383-1 – 2019.04
Requirement Limit
4 Maximum difference between branch piping
length
Twin: L2–L3≤limit 10m
Triple: L2–L4≤limit 10m
Double twin:
L2–L3≤limit
L4–L5≤limit
L6–L7≤limit
(L2+L4)–(L3+L7)≤limit
10m
5 Maximum height between indoor and outdoor Pair, twin, triple and double twin: H1≤limit 30m
6 Maximum height between indoors Twin, triple and double twin: H2≤limit 0.5m
(a) When piping length is <5m, a complete recharge of the unit is required. If the distance between indoor and outdoor unit is less than 5m, make
sure that the piping length is more than 5m by additional bending of the pipes.
Example
If the system layout is as follows… Then the requirements are…
Triple:
L2
L3
L4
H1
H2
L1
Østandard
1 5m≤L1+L4
2 L1+L2+L3+L4≤100m
3 L2≤20m
4 L2–L4≤10m
5 H1≤30m
6 H2≤0.5m
If size-up of liquid pipes is used, the indoor unit must be installed on
a lower location than the outdoor unit.
5.3.2 Refrigerant piping insulation
Use polyethylene foam as insulation material:
with a heat transfer rate between 0.041 and 0.052W/mK (0.035
and 0.045kcal/mh°C)
with a heat resistance of at least 120°C
Insulation thickness
Ambient
temperature
Humidity Minimum thickness
≤30°C 75% to 80% RH 15mm
>30°C ≥80% RH 20mm
5.4 Preparing electrical wiring
5.4.1 About preparing electrical wiring
INFORMATION
Also read the precautions and requirements in the
"General safety precautions" chapter.
INFORMATION
Also read "6.8.5 Specifications of standard wiring
components"[424].
WARNING
If the power supply has a missing or wrong N-phase,
equipment might break down.
Establish proper earthing. Do NOT earth the unit to a
utility pipe, surge absorber, or telephone earth.
Incomplete earthing may cause electrical shock.
Install the required fuses or circuit breakers.
Secure the electrical wiring with cable ties so that the
cables do NOT come in contact with sharp edges or
piping, particularly on the high-pressure side.
Do NOT use taped wires, stranded conductor wires,
extension cords, or connections from a star system.
They can cause overheating, electrical shock or fire.
Do NOT install a phase advancing capacitor, because
this unit is equipped with an inverter. A phase
advancing capacitor will reduce performance and may
cause accidents.
WARNING
All wiring MUST be performed by an authorised
electrician and MUST comply with the applicable
legislation.
Make electrical connections to the fixed wiring.
All components procured on-site and all electrical
construction MUST comply with the applicable
legislation.
WARNING
ALWAYS use multicore cable for power supply cables.