6 | Preparation
Installer reference guide
33
RZAG71~140N2V1+Y1
Sky Air Alpha-series
4P695307-1 – 2022.05
Ambient temperature Humidity Minimum thickness
≤30°C 75% to 80% RH 15mm
>30°C ≥80% RH 20mm
6.4 Preparing electrical wiring
6.4.1 About preparing electrical wiring
INFORMATION
Also read the precautions and requirements in the "2 General safety
precautions"[47].
INFORMATION
Also read "7.7.5Specifications of standard wiring components"[460].
WARNING
If the power supply has a missing or wrong N-phase, equipment might break
down.
Establish proper earthing. Do NOT earth the unit to a utility pipe, surge absorber,
or telephone earth. Incomplete earthing may cause electrical shock.
Install the required fuses or circuit breakers.
Secure the electrical wiring with cable ties so that the cables do NOT come in
contact with sharp edges or piping, particularly on the high-pressure side.
Do NOT use taped wires, stranded conductor wires, extension cords, or
connections from a star system. They can cause overheating, electrical shock or
fire.
Do NOT install a phase advancing capacitor, because this unit is equipped with an
inverter. A phase advancing capacitor will reduce performance and may cause
accidents.
WARNING
All wiring MUST be performed by an authorised electrician and MUST comply
with the applicable legislation.
Make electrical connections to the fixed wiring.
All components procured on-site and all electrical construction MUST comply
with the applicable legislation.
WARNING
ALWAYS use multicore cable for power supply cables.