7 Testing the product
7.1 Commission the control valve
After installation, commission the control valve to ensure that the equipment is working
properly.
Procedure
1. Inspect all bolts used to secure the control valve in-line to ensure that proper
mounting procedures have been followed and that flange connections are leak-
free.
2. Evaluate the system setup to ensure that all components are in the correct
operating sequence.
3. Evaluate the system setup to ensure that all components are in the correct
sequence for accurate product measurement. Some components are isolation
valves, strainers, flow straighteners, turbine meters, downstream sections, etc.
User manual Testing the product
P/N 3-9008-553 November 2020
User manual 41