Installing a 2U4N configuration in a 40U cabinet
NOTICE
After the installation is complete, you must complete the registration as described
Chapter 7 Update the Install Database on page 115
If you are installing a 2U4N configuration, refer to the following chapters in this
document:
Install the hardware components as described in: 2U4N Configuration Equipment
Installation on page 31
Connect the power, management, and data cables as described in the following:
l
Cabling the installation in a cabinet with single-phase power distribution: Wiring
Diagrams for a 2U4N Configuration in a Cabinet with Single-Phase Power
Distribution on page 67
l
Cabling the installation in a cabinet with 3-phase delta, or 3-phase wye power
distribution: Wiring Diagrams for a 2U4N Configuration in a Cabinet with 3-Phase
Delta or 3-Phase Wye Power Distribution on page 93
Before You Begin
Installing a 2U4N configuration in a 40U cabinet 15