2-Post Center-Mount Configuration
To install the Dell ReadyRails system using the two-post center-mount configuration, follow these steps.
1 Slide the plunger bracket rearward until it clicks into place and secure the bracket to the front post flange with two user-supplied
screws. See item 1 in Figure 19.
2 Slide the back bracket towards the post and secure it to the post flange with two user-supplied screws. See items 2 and 3.
3 Repeat this procedure for the second rail.
Figure 19. 2-Post Center-Mount Configuration
4-Post Threaded Configuration
To install the Dell ReadyRails system using the four-post threaded configuration, follow these steps.
1 For this configuration, remove the flange ear castings from each end of the ReadyRails assemblies. Use a Torx driver to remove the
two screws from each flange ear and remove each casting. See item 1 of the following figure. Retain the castings for future rack
requirements.
2 For each rail, attach the front and back flanges to the post flanges with two user-supplied screws at each end. See item 2 of the