Oil Change
The gearbox oil capacity is engraved onto the serial tag located on the top of the hood.
Initial (Bed-in) Oil Change:
The rst oil change must be carried out within the rst 50 hours of use under moderate operating
conditions. Thereafter, every 500 hours.
Change the gear oil after the rst 30 hours of severe operating conditions* (i.e. severe ambient
temperature conditions of +40°C or below 0°C, when augering, screw piling or core barrelling in hard
ground). Thereafter, every 300 hours.
OIL CHANGE SCHEDULE
MODERATE
OPERATING CONDITIONS
SEVERE
OPERATING CONDITIONS
*
PDD
(DIRECT DRIVE
ONLY)
FIRST OIL CHANGE
Within 3 months OR initial 50 hours
of use
Within the rst 30 hours of use Within the rst year
2ND OIL CHANGE PLUS
SUBSEQUENT OIL CHANGES
After 500 hours or 12 months of use
After 300 hours of use thereafter
(Drive requires a major stripdown,
inspection and rebuild)
Every 3 years there-
after
GEARBOX OIL: ISO EP 320 Extreme Pressure Mineral Gear Oil AUST/UK - PDD TO PD50
14 Maintenance
*Severe/extreme operating conditions include but not limited to ambient temperature conditions of +40°C (104°F) or below
0°C (32°F), working in hard ground, anchor applications and/or extended and continuous hours of operation. The gearbox oil