4.5 INSTALLATION PRECAUTIONS (LIVE BUS)
If the unit is to be installed on a live bus, the following precautionary measures must be
taken before installing the Measuring Head:
A.) Make sure that the cables are disconnected from the Measuring Head during
installation.
B.) Always follow all local and plant safety procedures.
WARNING
If the installation is to be made on a "live" bus, the Measuring Head cables must be
disconnected from the Measuring Head. A condition hazardous to the Measuring
Head and any person handling un-insulated cable-lead terminals will result if metal
parts of the Measuring Head contact the bus.
4.6 COMPLETING THE MEASURING HEAD INSTALLATION
With the Measuring Head temporarily installed and bus current off (or the head removed
from the bus for verification prior to installation), complete the following steps.
A.) Connect the interconnecting cable directly to the Measuring Head. Note that the
connectors are keyed and can only be connected one way.
B.) Before connecting the other end of the interconnecting cable to the Metering Unit,
perform the ohmmeter tests in Table 4.1. The tests are made from the open end of the
cable, looking back towards the Measuring Head. Record these values for future
reference.