The Power Rail has 5 lanes. This allows support for TN, IT and
TT three and one phase electrical grids.
Strip the cable cores by 12 mm. If the cable has flexible
conductors, it is recommended to use cable end sleeves on
all wires.
Tighten the screws with a torque of 5 Nm.
NOTICE! Terminations should be visually and mechanically
inspected before mounting the side panel.