Capillary installation:
Please follow the steps described below for capillary installation:
Turn off the lamp!!!
Open the door on unit front
panel. Loosen the screw on
black box and move it to left,
as shown on the pictures.
Open the box and install
capillary in slot as you can see
on the picture on right. Cleaned
part (window) of capillary
should be centered. In the
door center is a photodiode.
Do not touch it with bare
hands!
Close the box, move the screw
back and tighten it. Now the
capillary is fixed at correct
place.
Note: The unit is adjusted with testing capillary and at spectral light maximum (about
214 – 240 nm) shall be 100 % value of energy with new lamp.
Note: This unit does not include test cell, cell nor accessories of cell.
BELOW ARE STATED ONLY DIFFERENCES FROM BASIC TECHNICAL PARAMETERS OF THE UNIT.
Noise (Test capillary, 254 nm, TC 2 s, 10 Hz)
Drift (Test capillary, 254 nm)
Tube fuse T - 2.5A/250V, CSA
Mains cable 10A-250V 1.5 m