Installation and Site Acceptance Procedure
Section 6: Installation and Site
Acceptance Procedure
Any necessary installation and site acceptance procedures are discussed in the EL-O-Matic
E and P Series actuators Installation, Operation and Maintenance manual. The Installation,
Operation and Maintenance manual denes exercising of the actuator after installation and
denes testing after maintenance.
7
April 2017
SIL Safety Manual
DOC.SILM.EEP.EN Rev. 0
Section 6: Installation and Site Acceptance Procedure