4.3 Testing
S Connect the welding power source to the mains.
S Before switching on the welding power source, check that the power supply to
the board is 19 V.
S Connect the PEH control box to the 12--pole contact (XS4) in the welding power
source by way of the control cable.
S Switch on the power supply for the welding power source using the rotary switch
(QF) on the front panel.
S Make sure the power supply is interrupted when the emergency stop (QS) is
activated.
S Set the welding parameters over the PEH box.
S Start welding by pressing the START key.
S Make sure the relay in the welding power source is activated when the welding
starts.
S Check that different current and voltage values can be set over the PEH box.
S Mount the protective shields after finished work.