Installa on Instruc ons
Installa on of these units should be carried out by a competent person and appropriate codes of prac ce
adhered to, thus ensuring safe installa on.
Removal Of The Panels From The Pallet
The cabinets are of modular construc on with the wall panels and ancillary items delivered with retaining
shrink-wrap. This exterior should be removed, which a er cu ng the bands will allow all the components
to be removed and then checked for damage before placement in a convenient area for assembly.
There could be more than one crate – so check each one as above.
Installa on Of Panels And Equipment
The following instruc on is suggested as a method of installa on.
The ceiling panel is supplied with the refrigera on system / heater assembly pre-fi ed, ready for
installa on, once the wall panels are erected.
The cabinets are fl oorless and therefore require fi ng to a clean level fl oor.
The wall panels are a ached to the fl oor by inser ng them into PVC ‘U’ Channel. This is supplied cut and
mitred and should be fi ed to the fl oor prior to installa on
Loca on
Flat, level, clean, sound surface.
This appliance has a top mounted system and will need a minimum of 300mm clearance above the unit.
Panel Layout and Dimensions