FoxESS R100 - Inverter Startup Guide; Inverter Shutdown Procedure; Maintenance and Troubleshooting; Fault Alarm Reference

FoxESS R100
34 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
22
4
RS485A2
Reserved RS485 communication port
5
RS485B2
6
Meter485A
Meter communication port
7
Meter485B
8-16
Undefined
N/A
6.3 Inverter Start-Up
Please refer to the following steps to start-up the inverter:
a
)
Check if device is fixed well on the wall
;
b
)
Make sure all DC breakers and AC breakers are disconnected;
c
)
Ensure AC cable is connected to the grid correctly;
d
)
All PV panels are connected to inverter correctly; DC connectors that are not used should be
sealed by cover;
e
)
Connect the external DC breakers and AC breakers; and
f
)
Turn the DC switch to the "ON” position.
If the LED is not blue, please check the below:
-
All the connections are correct.
-
All the external disconnect switches are closed.
-
The DC switch of the inverter is in the "ON” position.
Note:
・
When starting the inverter for the first time, the country code will be set by default to the local
settings. Please check if the country code is correct.
・
Set the time on the inverter using the APP.
6.4 Inverter Switch Off
Please follow the below steps to switch off the inverter:
-
Switch off the inverter AC isolation switch.
-
Switch off the DC isolation switch and allow 15 minutes for the inverter to power down
completely.
Warning!
Power to the unit must be turned on only after installation work has been
completed. All electrical connections must be carried out by qualified personnel
in accordance with legislation in force in the country of installation.