Fujitsu AR 18 - Install the drain pipe

Fujitsu AR 18
26 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
En-15
(2)
Wall mounted type / Floor standing concealed type
3-15/16 in.
(100 mm)
or more
Downward gradient 0.10-
0.19 in. (2.5-5.0 mm)
Locally arranged pipe
GOOD
[O.D.1-1/16 in.
(27 mm)] or more
Air bleeding
Rise
PROHIBITED
Trap
Observe the following procedures to construct centralized
drain pipe ttings.
[O.D.1-5/16 in.
(33 mm)] or more
Downward gradient
1/100 or more
8.2. Install the drain pipe
(1) Be sure to use supplied Drain hose
1
and Hose band
2
2
Hose band
Drain
hole
1
Drain hose
Hard PVC side
Hose band
3/16 in. (4 mm) or less
13/16 in. (20 mm)
2
Hose band
1
Drain hose
Fasten the Hose band
2
at the position where
horizontal against earth (ground).
The Hose band
2
must be positioned at the right
side of the Drain hose
1
as in the gure.
(2) Be sure to connect Drain pipe with adhesive (polyvinyl
chloride) so that there is no leakage.
Applying
area of
adhesive
Joint pipe
(Field supply)
Drain pipe [3/4 in. (19 mm)
O.D.1-1/16 in. (27 mm)] (Field supply)
3/16 in. (4 mm) or less
CAUTION
Do not connect to the Drain hole with adhesive. Using
adhesive may cause damage and water leaks.
(3) After installing the Drain hose
1
, check if the drainage is
smooth.
CAUTION
To prevent excessive force on Drain hose
1
, avoid bends or
twists. (To bend or twist may cause water leaks.)
(4) After checking for drainage, attach the Drain hose
insulation B
3
to insulate, following the instructions as in
the gures.
To avoid space with Drain hose
1
and Hose band
2
,
press rmly the Drain hose insulation B
3
.
3
Drain hose
insulation B
Ensure there is
no space.
• STEP1~STEP3
Butt the insulation
against the unit.
STEP 1
Unit
Slit
Press rmly
Press rmly
STEP 2
Slit
Press rmly
9374342419_02_IM.indb 159374342419_02_IM.indb 15 2015/6/25 10:27:132015/6/25 10:27:13